Quantitative Aptitude • Time, Speed & WorkHard
A is twice as efficient as B. Working together, they finish a job in 24 days. How many days would A take to finish the job alone?
A. 72 days
B. 12 days
C. 48 days
D. 36 days✓ Correct Answer
💡 Solution & Explanation
If B does 1 unit of work per day, A does 2 units, so together they do 3 units per day. The whole job is 3 × 24 = 72 units. A alone takes 72 ÷ 2 = 36 days, and B alone would take 72 days. A, being faster, needs fewer days than B but more than the 24 days they take together.
More Quantitative Aptitude Time, Speed & Work questions
- A train 480 m long passes a person walking at 4 km/h in the same direction in 24 seconds. What is the speed…
- A train 220 m long passes a person walking at 6 km/h in the same direction in 11 seconds. What is the speed…
- A boat moves at 4 km/h in still water and the stream flows at 1 km/h. How long will the boat take to go 30 km…
- A car covers 1,404 km in 6 hours. What is its speed in metres per second?
- A train 275 m long passes a person walking at 6 km/h in the same direction in 11 seconds. What is the speed…