30 workers can build a wall in 26 days. How many days will 13 workers take to build the same wall, working at the same rate?

A. 60 days✓ Correct Answer
B. 11.27 days
C. 780 days
D. 43 days

💡 Solution & Explanation

The total work is 30 × 26 = 780 worker-days. More workers means fewer days, so divide: 780 ÷ 13 = 60 days. Multiplying instead (11.27 days) would mean more workers take longer, which cannot be right.