Quantitative Aptitude • Time, Speed & WorkEasy
10 workers can build a wall in 28 days. How many days will 20 workers take to build the same wall, working at the same rate?
A. 56 days
B. 14 days✓ Correct Answer
C. 280 days
D. 18 days
💡 Solution & Explanation
The total work is 10 × 28 = 280 worker-days. More workers means fewer days, so divide: 280 ÷ 20 = 14 days. Multiplying instead (56 days) would mean more workers take longer, which cannot be right.