Quantitative Aptitude • Time, Speed & WorkEasy

A can finish a piece of work in 10 days and B can finish it in 40 days. How many days will they take working together?

A. 25 days
B. 50 days
C. 8 days✓ Correct Answer
D. 30 days

💡 Solution & Explanation

In one day A does 1/10 of the work and B does 1/40. Together they do 1/10 + 1/40 = 1/8 of the work per day. So the whole work takes 8 days. Shortcut: ab ÷ (a + b) = 400 ÷ 50 = 8. Together they must be faster than either one alone.