MasteryExams
Quantitative Aptitude • Time, Speed & WorkHard

A is twice as efficient as B. Working together, they finish a job in 18 days. How many days would A take to finish the job alone?

A. 9 days
B. 36 days
C. 54 days
D. 27 days✓ Correct Answer

💡 Solution & Explanation

If B does 1 unit of work per day, A does 2 units, so together they do 3 units per day. The whole job is 3 × 18 = 54 units. A alone takes 54 ÷ 2 = 27 days, and B alone would take 54 days. A, being faster, needs fewer days than B but more than the 18 days they take together.