Quantitative Aptitude • Time, Speed & WorkEasy
A can finish a piece of work in 6 days and B can finish it in 12 days. How many days will they take working together?
A. 18 days
B. 6 days
C. 9 days
D. 4 days✓ Correct Answer
💡 Solution & Explanation
In one day A does 1/6 of the work and B does 1/12. Together they do 1/6 + 1/12 = 1/4 of the work per day. So the whole work takes 4 days. Shortcut: ab ÷ (a + b) = 72 ÷ 18 = 4. Together they must be faster than either one alone.
More Quantitative Aptitude Time, Speed & Work questions
- Two trains, each 120 m long, are running on parallel tracks in opposite directions at 36 km/h and 18 km/h.…
- Two trains, 230 m and 90 m long, are running on parallel tracks in opposite directions at 54 km/h and 18…
- Two trains, 110 m and 380 m long, are running on parallel tracks in opposite directions at 54 km/h and 72…
- A is twice as efficient as B. Working together, they finish a job in 6 days. How many days would A take to…
- A cyclist goes from one town to another at 30 km/h and comes back by the same road at 60 km/h. What is the…