MasteryExams
Quantitative Aptitude • Time, Speed & WorkHard

A is twice as efficient as B. Working together, they finish a job in 6 days. How many days would A take to finish the job alone?

A. 18 days
B. 9 days✓ Correct Answer
C. 12 days
D. 3 days

💡 Solution & Explanation

If B does 1 unit of work per day, A does 2 units, so together they do 3 units per day. The whole job is 3 × 6 = 18 units. A alone takes 18 ÷ 2 = 9 days, and B alone would take 18 days. A, being faster, needs fewer days than B but more than the 6 days they take together.